Photograph of I-15 Sieben North Pavement Preservation project area.
  • November 16 2026

HELENA, Mont. – The Montana Department of Transportation (MDT) and Jeffery Contracting Inc. are pausing construction on the I-15 Sieben North Pavement Preservation project for the 2026 construction season.

This year, crews rehabilitated approximately 4 miles of northbound Interstate 15 (I-15) from the Sieben Interchange (Exit 216) to about 5 miles south of Wolf Creek. Additionally, at the Spring Creek Interchange (Exit 219) crews improved drainage, rehabilitated the pavement on both ramps, and replaced the existing cattleguards.

“We are approximately halfway done with this project at the end of 2026,” said Matt Widhalm, MDT Engineering Project Manager. “We plan to complete the project in the 2027 construction season.”

In 2027, crews will return to rehabilitate the southbound lanes of I-15. This will include removal and replacement of more than a foot of degraded roadway material. Additionally, a seal and cover (chip seal) and final epoxy pavement markings are planned for the 2027 construction season.

Work on this project began in April 2026 and is anticipated to take 2 years to complete.

Visit 511mt.net for the most up-to-date information about oversized load restrictions and road conditions across Montana.

For more information about this project, visit the project website at mdt.mt.gov/pubinvolve/i15sieben.

MDT is a workforce of over 2,000 people across Montana determined to do all we can so that you arrive at your destination safely. Our mission is to build, operate, and maintain a safe and resilient transportation system. For more information, visit mdt.mt.gov.

###